· end 2026-11-1288d left
Open
Mark is waiting on you1 pending approval
- create_doctypeCreate a High-priority task on BR-2026-0142 to re-verify Citra Cryo hop lot 2026-4471's COA before the next dry-hop addition.In session MSESS-2026-00219
Mark intel
- Bottleneck2026-08-15from: standup meeting
The glycol control valve on FV4 still reads 'closed' under load — no spare on hand, and the OEM's lead time is 6 weeks. Cold crash on Broody is on hold until it's replaced or bypassed.
who: Ian Whitcomb
open transcript ↗ - Delayed2026-08-14from: standup meeting
Broody's release tasting moved right by 9 days (2026-09-07 → 2026-09-16) — taproom event calendar, not the beer. Colin has notified Seabrook Beverage Partners.
who: Colin Bass
open transcript ↗
Payment milestones
No milestones set.